NEW QUESTION # 36
5 A. --> 5 B. --> 5D --> 5F
`-->4C. --> 4E --^
The total float of activity E in the above diagram is:
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION # 37
The characteristics of a product that determine whether it meets certain requirements is known as the:
- A. success criteria.
- B. quality criteria.
- C. product criteria.
- D. acceptance criteria.
Answer: D
NEW QUESTION # 38
To ensure communication is most likely to be effective in the project, the project manager should:
- A. insist on a lower level of paper documents.
- B. ensure that everyone is copied On all emails.
- C. develop a communication plan.
- D. train project staff in the most up-to-date communication techniques
Answer: C
NEW QUESTION # 39
The project team comprises:
- A. all project stakeholders.
- B. the members of staff who are allocated full time to the project.
- C. the members of staff who report to the project manager and who carry out work on the project.
- D. all those responsible to the project manager who are working towards the project objectives.
Answer: D
NEW QUESTION # 40
We have an expert-written solution to this problem!
Who has ultimate responsibility for project risk?
- A. Project sponsor.
- B. Project manager
- C. Risk owner.
- D. Steering group.
Answer: A
NEW QUESTION # 41
What action is essential after a change has been approved?
- A. The related plans must be updated to reflect the change.
- B. The next change requested should be reviewed as quickly as possible.
- C. The actual impact of the change is assessed.
- D. The highlights of the change are communicated directly to the sponsor.
Answer: A
NEW QUESTION # 42
Which one of the following statements is true?
- A. Risk events always have beneficial effects on the project.
- B. Risk events always have detrimental effects on the project.
- C. Risk events can have either beneficial or detrimental effects on the project.
- D. Risk events have neither beneficial nor detrimental effects on the project.
Answer: C
NEW QUESTION # 43
When should test plans for quality control be agreed?
- A. When the live product is available for test.
- B. Prior to handover of the output
- C. During quality planning.
- D. At the end of the project.
Answer: C
NEW QUESTION # 44
Which of the following best describes a project environment?
- A. An understanding of the risks involved in the project.
- B. The structured method used to control the project.
- C. The type of organisation concerned with implementation.
- D. The context within which a project is undertaken.
Answer: D
NEW QUESTION # 45
Which of the following would not be considered as part of the post project review?
- A. Evaluation of the benefits of the project.
- B. Review of how the team worked together to solve problems and issues.
- C. Identification of the problems that arose and their likely causes.
- D. Review of the project's performance against the success criteria.
Answer: A
NEW QUESTION # 46
The purpose of project progress reporting is to:
- A. ensure stakeholder acceptance of project deliverables.
- B. enable the tracking of project deliverables.
- C. provide an increased total float.
- D. ensure a simpler critical path.
Answer: B
NEW QUESTION # 47
Governance could best be defined as:
- A. the framework of authority and accountability that defines and controls the outputs, outcomes and benefits from projects, programmes and portfolios.
- B. the framework that is used for selection, prioritisation and control of an organisation's projects and programmes in line with its strategic objectives and capacity to deliver D the framework used by the organisation and approved by the project board at project initiation that allows the definition of the terms of reference for the project.
- C. the framework that structures a review of the project, programme or portfolio and aids a decision to be made about whether to continue with the next phase or stage of progress.
Answer: A
NEW QUESTION # 48
When using a PESTLE analysis, a potential change in national government would be an example of a:
- A. potential change of government would not be considered in such an analysis.
- B. economic factor.
- C. sociological factor.
- D. political factor.
Answer: D
NEW QUESTION # 49
The primary purpose of a product breakdown structure (PBS) is to:
- A. define precisely what resources will be used on the project.
- B. map out the key project elements identified in the business plan
- C. define all the products that the project will produce.
- D. detail all the products in order of priority.
Answer: C
NEW QUESTION # 50
In developing a network the first task after listing the activities is to...
- A. Harmonise the activity to a calendar
- B. Determine the interdependencies of activities
- C. Define activity durations
- D. Determine float
Answer: B
NEW QUESTION # 51
How is project risk management best defined?
- A. A. technique to decompose the project into component parts or discrete groups for programming purposes.
- B. A. framework that allows requirements to be defined and reviewed so that the best project approach is determined.
- C. A. structured process to optimise project success by minimising threats and maximising opportunities.
- D. A. series of actions taken by a project team member or stakeholder to proactively avoid project threats.
Answer: C
NEW QUESTION # 52
......
Updated Nov-2024 Pass APM-PFQ Exam - Real Practice Test Questions: https://interfacett.braindumpquiz.com/APM-PFQ-exam-material.html