PDF (New 2024) Actual APM APM-PFQ Exam Questions [Q36-Q52]

Share

PDF (New 2024) Actual APM APM-PFQ Exam Questions

Dumps Moneyack Guarantee - APM-PFQ Dumps UpTo 90% Off


APM APM-PFQ Exam Syllabus Topics:

TopicDetails
Topic 1
  • Understand Project Life Cycles: This topic encompasses stating the phases of a typical linear project life cycle and an iterative project life cycle. It also includes defining the terms hybrid life cycle and 'extended project life cycle.
Topic 2
  • Understand Communication in the Context of a Project: The topic focuses on the advantages and disadvantages of different communication methods.
Topic 3
  • Understand Project Management Planning: This topic explains how the deployment baseline differs between linear and iterative life cycles. Additionally, the topic outlines the stakeholders of a project management plan, the purpose, and the typical content of a business case.
Topic 4
  • Understand Project Management and the Operating Environment: It includes defining the term project and stating the differences between a project and business as usual. It also covers defining 'project management' and its key purpose.
Topic 5
  • Understand Quality in the Context of a Project: This topic defines the term quality and outlines the purpose of quality management. It also includes defining quality planning.
Topic 6
  • Understand the Roles and Responsibilities within Projects: The topic focuses on project management roles and responsibilities. Moreover, the topic covers roles such as the project sponsor, project manager, project governance, project team members, and end users.

 

NEW QUESTION # 36
5 A. --> 5 B. --> 5D --> 5F
`-->4C. --> 4E --^
The total float of activity E in the above diagram is:

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: C


NEW QUESTION # 37
The characteristics of a product that determine whether it meets certain requirements is known as the:

  • A. success criteria.
  • B. quality criteria.
  • C. product criteria.
  • D. acceptance criteria.

Answer: D


NEW QUESTION # 38
To ensure communication is most likely to be effective in the project, the project manager should:

  • A. insist on a lower level of paper documents.
  • B. ensure that everyone is copied On all emails.
  • C. develop a communication plan.
  • D. train project staff in the most up-to-date communication techniques

Answer: C


NEW QUESTION # 39
The project team comprises:

  • A. all project stakeholders.
  • B. the members of staff who are allocated full time to the project.
  • C. the members of staff who report to the project manager and who carry out work on the project.
  • D. all those responsible to the project manager who are working towards the project objectives.

Answer: D


NEW QUESTION # 40
We have an expert-written solution to this problem!
Who has ultimate responsibility for project risk?

  • A. Project sponsor.
  • B. Project manager
  • C. Risk owner.
  • D. Steering group.

Answer: A


NEW QUESTION # 41
What action is essential after a change has been approved?

  • A. The related plans must be updated to reflect the change.
  • B. The next change requested should be reviewed as quickly as possible.
  • C. The actual impact of the change is assessed.
  • D. The highlights of the change are communicated directly to the sponsor.

Answer: A


NEW QUESTION # 42
Which one of the following statements is true?

  • A. Risk events always have beneficial effects on the project.
  • B. Risk events always have detrimental effects on the project.
  • C. Risk events can have either beneficial or detrimental effects on the project.
  • D. Risk events have neither beneficial nor detrimental effects on the project.

Answer: C


NEW QUESTION # 43
When should test plans for quality control be agreed?

  • A. When the live product is available for test.
  • B. Prior to handover of the output
  • C. During quality planning.
  • D. At the end of the project.

Answer: C


NEW QUESTION # 44
Which of the following best describes a project environment?

  • A. An understanding of the risks involved in the project.
  • B. The structured method used to control the project.
  • C. The type of organisation concerned with implementation.
  • D. The context within which a project is undertaken.

Answer: D


NEW QUESTION # 45
Which of the following would not be considered as part of the post project review?

  • A. Evaluation of the benefits of the project.
  • B. Review of how the team worked together to solve problems and issues.
  • C. Identification of the problems that arose and their likely causes.
  • D. Review of the project's performance against the success criteria.

Answer: A


NEW QUESTION # 46
The purpose of project progress reporting is to:

  • A. ensure stakeholder acceptance of project deliverables.
  • B. enable the tracking of project deliverables.
  • C. provide an increased total float.
  • D. ensure a simpler critical path.

Answer: B


NEW QUESTION # 47
Governance could best be defined as:

  • A. the framework of authority and accountability that defines and controls the outputs, outcomes and benefits from projects, programmes and portfolios.
  • B. the framework that is used for selection, prioritisation and control of an organisation's projects and programmes in line with its strategic objectives and capacity to deliver D the framework used by the organisation and approved by the project board at project initiation that allows the definition of the terms of reference for the project.
  • C. the framework that structures a review of the project, programme or portfolio and aids a decision to be made about whether to continue with the next phase or stage of progress.

Answer: A


NEW QUESTION # 48
When using a PESTLE analysis, a potential change in national government would be an example of a:

  • A. potential change of government would not be considered in such an analysis.
  • B. economic factor.
  • C. sociological factor.
  • D. political factor.

Answer: D


NEW QUESTION # 49
The primary purpose of a product breakdown structure (PBS) is to:

  • A. define precisely what resources will be used on the project.
  • B. map out the key project elements identified in the business plan
  • C. define all the products that the project will produce.
  • D. detail all the products in order of priority.

Answer: C


NEW QUESTION # 50
In developing a network the first task after listing the activities is to...

  • A. Harmonise the activity to a calendar
  • B. Determine the interdependencies of activities
  • C. Define activity durations
  • D. Determine float

Answer: B


NEW QUESTION # 51
How is project risk management best defined?

  • A. A. technique to decompose the project into component parts or discrete groups for programming purposes.
  • B. A. framework that allows requirements to be defined and reviewed so that the best project approach is determined.
  • C. A. structured process to optimise project success by minimising threats and maximising opportunities.
  • D. A. series of actions taken by a project team member or stakeholder to proactively avoid project threats.

Answer: C